Table 1  

Summarised Cost Schedule and Financing Plan

 

 

Total Financing Requirement in '000

Non-CMA

CMA

Total

 

Maloti Equivalent

 

 

 

 

Capital Costs

 

 

 

 

 

Mohale Tunnel Construction

245,254

650,952

896,205

 

 

Mohale Dam Construction

289,021

276,538

565,559

 

 

Matsoku Diversion Construction

50,724

224,226

274,949

 

 

Infrastruct. Constr. – Maseru Bypass & Road Rehab.

 

112,585

112,585

 

 

Infrastruct. Constr. – Mohale Camp

 

120,030

120,030

 

 

Infrastruct. Constr. – Access Roads

 

302,029

302,029

 

 

Infrastruct. Constr. – Construction Power

 

54,707

54,707

 

 

Infrastruct. Constr. – Telecommunications

 

11,556

11,556

 

 

Major Works Engineering – Mohale Tunnel

51,358

64,016

115,374

 

 

Major Works Engineering – Mohale Dam

40,024

49,035

89,059

 

 

Major Works Engineering – Matsoku Diversion

 

28,210

28,210

 

 

Other Engineering

 

112,579

112,579

 

 

Environ. – Compensation & Resettlement

 

491,905

491,905

 

 

Environ. – Development

 

65,569

65,569

 

 

Environ. – Natural Environ. & Heritage

 

72,804

72,804

 

 

Environ. – Public Health

 

49,966

49,966

 

 

Administration

141,408

264,505

405,913

 

Sub-total

817,789

2,951,210

3,768,999

 

Finance Costs

 

 

 

 

 

Charges capitalised during construction

73,054

544,818

617,872

 

 

Charges paid during construction

141,090

1,647,167

1,788,257

 

Total Capital and Financing Costs

1,031,932

5,143,195

6,175,127

 

 

 

 

 

 

 

Ultimate Funding Sources in '000 Maloti

Non-CMA

CMA

Total

 

 Equivalent

 

 

 

 

Funding for Capital Costs

 

 

 

 

 

Trinkaus & Burkhardt KgaA

150,888

 

150,888

 

 

Midland/Credit Lyonnais – Export Credit

75,718

 

75,718

 

 

Midland/Credit Lyonnais – Comm

23,337

 

23,337

 

 

RSA CRP (EIB) - Mohale Dam

297,320

 

297,320

 

 

EIB I – Matsoku Diversion

274,949

 

274,949

 

 

World Bank I - Phase IB Loan

205,391

 

205,391

 

 

World Bank II - Phase IA Loan carried over to IB

31,651

 

31,651

 

 

DBSA (D38) - Mohale Camp