Conceptual Overview
Phase 1A
- Katse Dam (1,950 million m3)
- Transfer Tunnel (45 Km)
- 'Muela Power Station (72 MW)
- 'Muela Dam
Phase 1B
- Mohale Dam (958 million m3)
- Interconnecting Tunnel (30 Km)
- Matsoku Wier and Transfer Tunnel (6.4 Km)
Phase 2 (possible future phase)
- Mashai Dam (3,306 million m3)
- Second Delivery Tunnel from Katse Dam to Ash River Outfall
Phase 3 (possible future phase)
- Tsoelike Dam (2,223 million m3) and Pumping Station
Phase 4 (possible future phase)
- Ntoahae Dam and Pumping Station
|