Lesotho Highlands Water Project Phase 2 Feasibility StudyVolume 2, Issue 1 August 10, 2006 PHASE
2 FEASIBILITY STUDY A bi-national
Study Management Committee (SMC) is responsible for the award and subsequent
supervision of the study: the SMC Team Leaders are Peter van Niekerk for the RSA
and Sixtus L. Tohlang representing Government of Lesotho (GOL). THE
ENGINEERING STUDIES The staged
development of the LHWP can only be planned in relation with the expected growth
in RSA water demand, and depend on the rates of growth in such demand: later
phases, if the demand for them materializes, may therefore be some years away. Phase 2
options include dams at sites in the northwest in Lesotho, at Polihali near
Mokhotlong from which area water could flow by gravity through a tunnel into the
Katse Dam Reservior, or in a more central area such as Taung or Mashai from
which water have to be pumped up into Katse Dam which was built during the LHWP
Phase 1 system. Phases beyond
Phase 2 could be planned in a number of different ways, depending to some extent
on what Phase 2 option is selected. The possible dam sites include Phase 3 (Tsoelike),
Phase 4 (Ntoahae, Malatsi or Lebelo). The water from Lebelo could flow by
gravity to the South if the other dams are constructed there, or be pumped via a
tunnel to the existing dam at Mohale. The added
advantage of Phase 2 is that the 45 km tunnel linking Katse Dam and the ‘Muela
Hydropower station will be able to take the planned 17m3/sec from
Phase 2 thus postponing doubling of the transfer tunnel to Phase 3 of the
Project. The 15 km delivery tunnel from the Hydropower Station to RSA has some
constrictions that will have to be upgraded to take the Phase 2 flow. As part of
the study, Lesotho Hydropower needs are being assessed as well as PUBLIC
PARTICIPATION PLAN The Public
Participation Process is designed to engage all stakeholders, in The main
issues arising from the consultations so far include compensation for impacts
likely to result from the project, arrangements for resettlement where
necessary, and issues of opportunity that may result from the Project including
employment, facilities and community development. The second
stage of the process will involve re-engaging with all of the communities to
explain what options have been selected as most likely to be viable. The study
will focus on the selected options in more detail, taking issues that the
communities have identified into consideration. The necessary responses to these
issues will be assessed as part of the economics and viability, and the outcome
will be an identified possible next phase of the LHWP that can compete with any
alternative project on the basis of cost-effectiveness. The study is
due for completion in December 2007 and its results will be tabled to the Click
here for
© copyright LHWP |
|