Katse Dam
Transfer Tunnel
'Muela Hydropower Station and Tailpond Dam
Ash River Outfall

 

Delivery Tunnels

The delivery tunnel is made up of two sections: the Delivery Tunnel South, from the 'Muela power station to the Lesotho- South Africa border, and the Delivery Tunnel North, from the border to the Ash River Outfall in South Africa.

Construction of the Delivery Tunnel South went smoothly. The l5km tunnel boring machine (TBM) excavation was completed 20 months ahead of schedule, realising a saving of M85,7 million on the original R42l,6 million contract. Included in the structure are two steel-lined sections that form the crossings under three rivers. Under the Ngoajane River is an l8m section of pipe housing the flow meters that measure the volume of water delivered from Lesotho to South Africa. This part o(the tunnel was the first part of Phase lA to be completed.

The 22km-long Delivery Tunnel North was also completed ahead of time (by three months) and under budget (a R52 million saving). Only one TBM was used, with the tunnel being lined concurrently with precast concrete segments, thus saving time. The first section of the tunnel, under the Caledon River (the South Africa-Lesotho border) was constructed using traditional drill-and-blast techniques, and is steel-lined.

 

  Katse to 'Muela Delivery Tunnel South Delivery Tunnel North
Construction Time Mid 1992 to September 1994 using 3 tunnel boring machines in single drives February 1992 to August 1993 using 1 machine in 3 drives July 1992 to February 1995 using 1 machine in 2 drives
Length 13km + 15km + 17.5km 1.8km + 5.3km + 5.7km 11km + 16km
Best Distance 1 344m in a month 1 324m in a month 1 078m in a month

s website is under reconstruction, we apologise for the inconsistancy among web documents.